SERVICES

Con Ed, Avenue A Substation, Manhattan, NY

FSI Installed a series of MacLean-Dixie P35 pipe piles at Con Edison’s East 6th Street substation in New York to support a new transformer unit. The project required FSI to perform a load test to 50 kips with a net settlement of .126″. The foundation was dug to ten feet and the piles were installed to 10,500 ft*lbs ranging from 50-60 feet in depth. All pile locations were dug by hand to a depth of 4 feet prior to pile installation. The piles were installed within a 2’x 2′ footprint. The East 6th Street Substation serves the entire East Village, home to roughly 50,000 residents. The new transformer replaces the original (built in the 1950s) with a larger design that will allow the substation to deliver more electricity to the neighborhood.

  • slider-image
  • slider-image
  • slider-image
  • slider-image
  • slider-image
  • slider-image
  • slider-image
  • slider-image
  • slider-image
  • slider-image
  • slider-image
  • slider-image
  • slider-image
  • slider-image
  • slider-image
  • slider-image
  • slider-image
  • slider-image
  • slider-image
  • slider-image
Project Name and Location:
Con Edison of New York Substation. Avenue A, New York, NY
Project Date:
January 2013
Project Type:
New Construction, Transformer Rehabilitation
Piles Specification:
P35 Series Pipe Piles (8’ x 10’ x 12’ lead connected to a P35 extension)
Soil & Embedment Depth:
Pile depth ranging from 50-60 feet. Pile locations were dug to a depth of 4 feet.
Project Timeline:
1 Week